Description of the Alternatives

This appendix provides a more detailed description of the alternatives that were evaluated in the Framework process. All seven alternatives were analyzed using the Bonneville Power Administration’s (BPA) HYDSIM computer model. Alternatives 1, 4, and 6 were analyzed by the Northwest Power Planning Council (NWPPC) staff. Alternative 2 was analyzed by the Columbia River Intertribal Fish Commission (CRITFC). Alternatives 3, 5, and 7 were analyzed by the BPA.

These analyses should be considered preliminary and subject to change. In all cases, the general intent of each alternative was captured, however, in some cases not all aspects of the strategy could be modeled due to lack of data or time. This appendix describes the seven alternatives as they were modeled. Because of that, it should be noted that the descriptions below and in the summary in Table F-23 could differ from other descriptions or summaries of the Framework alternatives.

In the discussion below, the vision for each alternative is summarized, followed by a description of the required changes to the hydroelectric system’s operation in order to implement that vision. All actions taken are relative to the National Marine Fisheries Service’s (NMFS) 1998 biological opinion.

We begin with a description of Alternative 4 because this scenario is closest to current river operations under the 1998 biological opinion. The analysis for Alternative 4 is exactly the same as the 1998 biological opinion as modeled by BPA. This option calls for experimentation with flood control elevations, integrated rule curves, spill, and other potentially helpful operations. However, because these are all yet to be tested, none was modeled in the analysis for this alternative.

 

Alternative 4: Conduct Managed Experiments Before Making Major System Changes

In this alternative, 10 to 12 years of carefully designed experiments will be conducted to assess the effectiveness of various approaches to recovery of Columbia River fish and wildlife. These ambitious experiments are obviously also expected to help the listed species. Findings will be evaluated before further capital improvements or decisions on major dam reconfiguration are made.

General Modeling Assumptions

The modeling assumptions for this alternative reflect the intent of the NMFS’ 1998 biological opinion. All project non-power requirements are derived from the Pacific Northwest Coordination Agreement (PNCA) plant data book, specifically from the 1997 operating year planning process.

The 50 years of historic stream flows used in this analysis come from the document entitled "Modified Streamflows 1990 Level of Irrigation," dated July 1993. They contain the 1990 level of irrigation depletion. Slight adjustments to these 1990-level modified stream flows were made by the U.S. Bureau of Reclamation to update Grand Coulee’s pumping schedule for the Columbia Basin Project.

Flood control curves (Upper Rule Curves or URCs) were calculated by using forecasted volume runoff based on the Kuehl Moffitt Report dated July 1986. The data incorporate a shift of system flood control from Dworshak and Brownlee (when the April-through-July runoff volume forecasts are less than 3.2 million acre-feet (MAF) and 5.8 MAF, respectively) to Grand Coulee and incorporate the 2.08 MAF Mica and 5.1 MAF Arrow flood control allocation. Flood control will take precedence over all non-power requirements, except the International Joint Commission (IJC) 1938 Order at Kootenay Lake.

Plant Specific Modeling Assumptions

Mica, Duncan, and Arrow

reservoirs are operated according to the Detailed Operating Plan (DOP) developed jointly by the Entities as defined in the Canadian Treaty.

Additionally, Arrow will store up to 1 MAF of water in years when the January-through-July runoff volume forecast (95 percent confidence level) at The Dalles is less than 90 MAF. This additional water will be released April 16 through June 30, as needed, to meet the McNary flow augmentation targets. If conditions change by April 1 so that flow augmentation water is no longer needed, any amount already in storage at Arrow will be released by April 15.

Non-treaty water stored at the Mica Reservoir is not used in this analysis.

Libby

 is operated to meet power needs from September through December, subject to monthly minimum draft limits computed to achieve its December flood control elevation (2411.0 feet or 1502.2 Ksfd). From January through mid-April, outflow at Libby is reduced to its minimum requirement unless flood control would be violated. It should be noted that Libby can violate its flood control limit for the IJC operation at Kootenay Lake.

Libby

 is operated mid-April through July for protection of white sturgeon in all water conditions by releasing water to help maintain minimum flow requirements at Bonners Ferry. The minimum flow requirement at Bonners Ferry is 15,000 cubic feet per second from May 1 through May 9. From May 10 through June 20, Libby’s outflow reflects a full turbine operation. From June 21 through July 11, Bonners Ferry minimum flow requirement is 11,000 cubic feet per second. Table F-1 shows the computed Libby minimum outflow requirement for white sturgeon protection. Libby’s maximum outflow from mid-April through August is 25,000 cubic feet per second, which is the assumed full turbine operation without spill.

In August, Libby can be drafted as low as 20 feet from full (2439.0 feet or 2061.3 Ksfd) to contribute to flow augmentation at McNary Dam.

Kootenay Lake

 will be operated as necessary, up to free flow, to maintain the lake level below the IJC rule curve and the calculated "allowable elevation at Queens Bay." This is implemented using the five-step method as developed by BPA and the U.S. Army Corps of Engineers (COE). After August 31, the lake level may be raised to elevation 1745.32 feet at the Queens Bay gage. This maximum elevation at Queens Bay is in effect through January 7. After January 7 the lake will be lowered to at least 1,744 feet by February 1, 1,742.4 feet by March 1, and 1,739.32 feet by April 1. From April 1st through August 31, if the lake elevation exceeds 1739.32 feet at the Queens Bay gage, the lake will be operated using the "allowable elevation" calculation until the elevation at the Nelson gage gets back to 1,743.32 feet.

Hungry Horse

 is operated to meet power needs from September through December, subject to monthly draft limits of 3,531 feet (1215.7 Ksfd) in September, 3,526 feet (1162.0 Ksfd) in October, 3,521 feet ( 1108.3 Ksfd) in November, and 3,515.0 feet (1049.0 Ksfd) in December. From January through March, outflow at Hungry Horse is reduced to its minimum requirement unless flood control would be violated. From April through July, Hungry Horse operates at or near flood control elevations.

In August, water from Hungry Horse is used for flow augmentation at McNary, subject to drafting limits of 3,550 feet (1427.7 Ksfd) by August 15 and 3,540 feet (1312.3 Ksfd) by August 31. Hungry Horse is operated to support the Columbia Falls minimum flow requirement of 3,500 cubic feet per second and Columbia Falls’ maximum flow limit of 4,500 cubic feet per second from October 15 through December 15. Hungry Horse’s maximum outflow from mid-April through August is set to its powerhouse hydraulic capacity plus 3,000 cubic feet per second spill.

 

Table F-1

White Sturgeon Minimum Flow Requirements at Libby Dam

(thousands of cubic feet per second)

 

May

 

June

 

July

 

   

May

 

June

 

July

 

1929

19.34

18.54

6.04

 

1954

15.72

15.20

3.68

1930

20.17

18.41

5.75

 

1955

18.45

15.54

4.77

1931

19.66

19.26

5.95

 

1956

15.19

16.36

5.07

1932

17.18

16.77

5.26

 

1957

16.67

18.27

5.74

1933

17.67

14.31

4.19

 

1958

18.21

19.14

5.95

1934

18.32

18.44

5.71

 

1959

17.65

16.02

5.01

1935

17.77

16.91

5.26

 

1960

18.53

17.12

5.48

1936

18.57

18.60

5.93

 

1961

17.04

15.81

5.49

1937

18.77

17.36

5.54

 

1962

19.09

18.00

5.75

1938

17.62

16.92

5.23

 

1963

19.39

18.14

5.56

1939

19.16

18.63

5.67

 

1964

18.40

16.00

5.38

1940

19.66

19.13

6.11

 

1965

18.12

16.82

5.53

1941

20.44

19.28

6.00

 

1966

18.22

17.00

5.57

1942

19.10

17.08

4.73

 

1967

17.97

15.20

5.36

1943

18.37

16.43

4.55

 

1968

19.08

17.72

5.49

1944

20.90

19.42

6.03

 

1969

17.15

16.90

4.64

1945

18.88

18.11

5.75

 

1970

18.54

17.86

5.78

1946

17.32

16.96

5.20

 

1971

16.49

16.51

4.69

1947

17.07

17.78

5.63

 

1972

17.17

16.38

5.13

1948

16.42

15.41

5.00

 

1973

19.71

18.96

6.12

1949

16.91

18.42

5.90

 

1974

17.26

13.73

4.45

1950

16.88

14.33

4.07

 

1975

17.54

15.80

5.32

1951

16.83

17.58

5.27

 

1976

17.47

18.05

5.51

1952

17.68

17.89

5.09

 

1977

20.75

19.70

6.02

1953

17.84

17.04

5.41

 

1978

18.45

17.98

5.55

 

Albeni Falls

 is operated in September to 2,060.0 feet (465.7 Ksfd). In October through April, Albeni Falls is operated to 2,055.0 feet (279.0 Ksfd). In May, Albeni Falls is operated to 2,057.0 feet (325.7 Ksfd). From June through August, Albeni Falls is operated to full pool elevation or 2,062.5 feet (582.4 Ksfd).

Grand Coulee

 is operated to meet power needs from September through December, subject to draft limits of 1,280 feet in September and October, 1,275 feet in November and 1,265 feet in December. From January through mid-April, Grand Coulee is operated to a set of minimum elevation limits that are designed to get the reservoir to its flood control elevation by April 15 with the desired probability. During this time period, Grand Coulee also provides water releases to maintain the required minimum flow at Priest Rapids for the Vernita Bar operation (described below). From mid-April through June, Grand Coulee may be drafted to the lower of flood control or 1,280 feet to support McNary flow augmentation targets. In July and August, Grand Coulee may be drafted as low as 1,280 feet (2216.4 Ksfd) to support McNary flow augmentation targets. At-site minimum flow is 30,000 cubic feet per second. Grand Coulee is subject to a daily drawdown limit of 1.3 feet per day.

Vernita Bar

 minimum flows (measured at Priest Rapids Dam) for December through May vary by water condition, with minimum flows established as the lesser of 68 percent of the Wanapum’s October or November flows or 70,000 cubic feet per second. Values less than 70,000 cubic feet per second are rounded to the nearest 5,000 cubic feet per second. This minimum flow is controlled by releases from Grand Coulee Reservoir.

Upper Snake

 River dams are operated in a manner to attempt to provide 427,000 acre-feet of water for spring and summer flow augmentation each year. Since these dams are not modeled explicitly, the effect of their operation is incorporated into Brownlee Dam’s inflow data. The full 427,000 acre-feet of additional water from these projects is not always available.

Brownlee

 will be operated to the fixed operation submitted for PNCA planning. In September, Brownlee is drafted an additional 100,000 acre-feet for flow augmentation. From October through December, Brownlee attempts to maintain an outflow as close to 9,000 cubic feet per second as possible. In October a draft limit of 2,051.0 feet (325.7 Ksfd) is imposed during dry years and a limit of 2034.6 feet (240.1 Ksfd) is imposed during median to high water years. From January through April, Brownlee’s outflow reduced to fill the reservoir. In May, Brownlee is drafted to or maintained at 2,069 feet (436.4 Ksfd). The reservoir is maintained at 2,069 feet in June. In July, Brownlee is drafted down to 2,067.0 feet (423.1 Ksfd). This elevation is held in July and August.

Dworshak’s

outflow is reduced to its minimum requirement of 1,300 cubic feet per second from September to March in order to store as much water as possible for the salmon migration period. From April through August Dworshak is drafted to meet Lower Granite flow augmentation targets. Dworshak may only be drafted to 1,520 feet by August 31. During the migration period, Dworshak’s outflow is limited to 14,000 cubic feet per second and is limited to 25,000 cubic feet per second in all other periods for downstream flood control.

Generation at the four Lower Snake and four Lower Columbia dams (Lower Granite, Little Goose, Lower Monumental, Ice Harbor, McNary, John Day, The Dalles, and Bonneville) is further reduced with the inclusion of juvenile bypass fish spill requirements, as reflected in the 1998 biological opinion. If the regulated outflow at Lower Granite is less than 100,000 cubic feet per second then there is no spill at the project; otherwise, spill will be 80 percent of instantaneous flow at Lower Granite. If the regulated outflow at Lower Granite is less than 85,000 cubic feet per second then there is no spill at Little Goose and Lower Monumental; otherwise, spill will be 80 and 81 percent of instantaneous flow at Little Goose and Lower Monumental, respectively. Bonneville has a daytime spill cap of 75,000 cubic feet per second from 0600 to 1800 hours. Juvenile bypass fish spill at federal projects (percent of outflow), limited by spill caps, isas shown in Table F-2.

Table F-2

Bypass Spill Requirements at Federal Dams

(percent of outflow)

Projects

 

Mar

 

Apr1

 

Apr2

 

May

 

Jun

 

Jul

 

Aug1

 

Aug2

 

Cap (cfs)

 

Bonneville

.230

 

.499

.680

.680

.770

.770

.770

90,000

The Dalles

   

.469

.640

.640

.640

.640

.640

300,000

John Day

   

.121

.165

.165

.430

.430

.430

60,000

Ice Harbor

 

.108

.270

.270

.413

.700

.700

.700

40,000

McNary

   

.183

.250

.250

     

60,000

Lower Monumental

 

.162

.405

.405

.270

     

20,000

Little Goose

 

.160

.400

.400

.267

     

25,000

Lower Granite

 

.160

.400

.400

.267

     

22,500

 

Juvenile bypass spill requirements at non-federal projects are described below in Table F-3. Spill requirements at Rock Island Dam are provided in Table F-4.

The 1998 biological opinion calls for flow objectives at McNary Dam from April 20 through August. From April 20 through June, the flow target ranges from 220,000 to 260,000 cubic feet per second based on the forecasted January-through-July runoff volume at The Dalles. In years when the runoff volume is predicted to be less than 85 MAF, the flow target is set to 220,000 cubic feet per second. In years when the runoff volume is expected to be higher than 105 MAF, the target is 260,000 cubic feet per second. For years in between, a linear interpolation between the low and high target values is used. For July and August, the flow target is set to 200,000 cubic feet per second. The sequence for releasing water from upstream reservoirs for flow augmentation is to draft Grand Coulee first followed by Libby and then Hungry Horse.

The1998 biological opinion flow objectives for Lower Granite Dam range from 85,000 to 100,000 cubic feet per second from April 1 through June. When the forecasted April-through-July runoff volume at Lower Granite is less than 16 MAF, the target is set to 85,000 cubic feet per second. When the forecasted runoff volume is expected to be higher than 20 MAF, the target is 100,000 cubic feet per second. For years in between, a linear interpolation is used. For July and August, the flow objective ranges from 50,000 to 55,000 cubic feet per second again depending on the same forecasted runoff volume at Lower Granite.

Table F-3

Bypass Spill Requirements at non-Federal Dams

(percent of outflow)

Projects

 

Apr1

 

Apr2

 

May

 

Jun

 

Jul

 

Aug1

 

Aug2

 

Cap (cfs)

 

Wells

0.0

6.5

6.5

0.0

6.5

2.5

0.0

10,000

Rocky Reach

0.0

12.0

15.0

4.0

8.0

4.0

0.0

5,000

Wanapum

0.0

10.0

25.0

2.5

14.2

20.0

1.25

10,000

Priest Rapids

0.0

7.0

35.0

5.8

13.5

20.0

6.3

25,000

 

Table F-4

Bypass Spill Requirements at Rock Island Dam

(cubic feet per second)

Period

 

Period Average Spill

 

April 1-15

4,800

April 16-30

19,300

May

23,000

June

23,000

July

23,000

August 1-15

19,300

August 16-31

4,800

 

John Day

 is operated at an elevation of 262.5 feet from mid-April through September. From October through mid-April, John Day is operated to an elevation of 265 feet.

Lower Snake River dams (Lower Granite, Little Goose, Lower Monumental and Ice Harbor) are operated within one foot of their minimum operating pool (MOP) elevations from approximately April 10 through August 31. Lower Granite will continue to operate within one foot of MOP through November 15. Minimum operating pool elevations are; 733 feet at Lower Granite, 633 feet at Little Goose, 537 feet at Lower Monumental, and 437 feet at Ice Harbor. During the rest of the year Lower Granite, Little Goose, Lower Monumental, and Ice Harbor will operate at normal pool elevations or 738, 638, 540 and 440 feet, respectively.

 

Alternative 1: A Connected Self-Sustaining Ecosystem

This alternative describes an ecosystem that has an increased ability to be self sustaining in a state consistent with the biological needs of native fish and wildlife. The system would provide increased levels of ecological services, intrinsic benefits as well as significant conventional economic services. The system would support diverse, naturally spawning fish and wildlife that transcend current blockages. Fish and wildlife spawn and function naturally. Human services such as power generation and transportation are mostly eliminated in the Lower Snake and reduced in the Columbia River.

Modeling Assumptions

To achieve river flows that mimic the natural hydrograph, all reservoirs are held as full as possible (i.e., to flood control elevations) in all months except August. This strategy essentially allows the dams to pass inflows while maintaining high reservoir elevations for resident fish, recreation, irrigation, etc. In high runoff years (i.e., wet years) reservoirs would be drafted in late winter or early spring to make space for the anticipated runoff and protect against flooding.

In this alternative the 1998 biological opinion flow objectives in the Snake and Columbia rivers are removed. In their place, flow targets of 135,000 and 105,000 cubic feet per second are added at The Dalles Dam for the first and second half of August, respectively. Also, flow targets of 30,000 and 20,000 cubic feet per second are added at Lower Granite Dam for the same time period. These flow objectives help raise river flows above the natural hydrograph in August for both temperature control and for increased river velocity.

Flood control limits (i.e., ceiling elevations) are modified at Libby, Hungry Horse and Grand Coulee dams using a variable-flow methodology (VARQ) developed by the COE. This change provides more space to store water in the early spring months while not increasing the risk of flooding downstream. In general, the flood control elevations at Libby and Hungry Horse dams are raised and the limits at Grand Coulee Dam are lowered somewhat.

Year-round minimum-elevation limits have been developed for Libby and Hungry Horse reservoirs to protect resident fish populations. These limits are often referred to as biological rule curves. This alternative calls for the implementation of these rule curves. Unfortunately, these curves occasionally conflict with the flood control operation. In order to eliminate this conflict, the biological rule curves have been integrated with the variable-flow flood control limits to create what are known as the "integrated rule curves." These integrated rule curves are included in this alternative but because the system is operated to flood control elevations nearly year round, this action is unnecessary. Similar integrated rule curves for Grand Coulee and Dworshak reservoirs are yet to be fully developed.

Libby, Hungry Horse, Grand Coulee, and Dworshak reservoirs are drafted in August, if necessary, to achieve the flow objectives at The Dalles and at Lower Granite as defined above. Libby is drafted no lower than 2,455 feet (the 1998 biological opinion limit is 2,440 feet). Hungry Horse is not drafted below 3,555 feet (the 1998 biological opinion limit is 3,540 feet). Grand Coulee is not drafted below 1,287 feet (the 1998 biological opinion limit is 1,280 feet) and Dworshak is not drafted lower than 1,590 feet (the 1998 biological opinion limit is 1,520 feet).

Of the 12 MAF of storage in the Mica Reservoir in Canada, 7 MAF are a part of the Canadian Treaty with the United States. That storage along with storage in other Canadian and U.S. reservoirs is called "treaty" storage. The total treaty storage in the system is managed to provide the most efficient use of that water, limited to whatever non-power constraints are in effect. The remaining 5 MAF of storage in Mica is referred to as "non-treaty" storage and is used to supplement the use of treaty water. The U.S. and Canada equally share the benefits of the non-treaty water. In this alternative, 1 MAF of non-treaty water stored in the Mica Reservoir is used for flow augmentation in August.

The four Lower Snake River dams (Lower Granite, Lower Monumental, Little Goose, and Ice Harbor) and John Day and McNary dams are "breached" in this alternative. In this case the word "breached" means that, to the extent possible, the dams are kept in place while the river is routed around them. According to the COE, this is the least costly method of providing natural flows. At the same time, this allows the existing generators at the dams to be converted to synchronous condensers, if necessary, to support transmission stability.

Spill requirements are not necessary at dams that have been breached. For other dams, this alternative includes the same spill provisions as in the 1998 biological opinion.

 

Alternative 2: A Reconnected Ecosystem To Support Salmon Harvest

This alternative describes an ecosystem that has an increased ability to sustain a condition that supports harvestable salmonid populations with decreased amounts of external support. Other biological elements (e.g., resident fish and wildlife) would develop within communities consistent with this primary goal. The system would provide increased levels of harvest, ecological services, and intrinsic benefits as well as significant conventional economic services.

A primary goal is to restore diverse and harvestable salmon stocks. In this alternative, the Columbia Basin is a largely naturally-functioning, self-sustaining ecosystem aimed at increasing and sustaining salmon harvest. Areas above and below the dams are treated as separate systems. Power generation and navigation are reduced in the Columbia River and drastically reduced in the Lower Snake River.

Modeling Assumptions

Water in federal reservoirs along with some Canadian and Upper Snake Basin water is used to attempt to achieve the flow objectives at The Dalles and at Lower Granite dams listed in Table F-5. The current flow objectives (under the 1998 biological opinion) at Priest Rapids Dam are not changed in this alternative.

Table F-5

Flow Objectives for Alternative 2

(cubic feet per second)

Period

 

The Dalles Dam

 

Lower Granite Dam

 

April 1-15

210,000

 

April 16-30

240,000

 

May

400,000

115,000

June

450,000

100,000

July

300,000

63,000

August 1-15

200,000

46,000

August 16-31

140,000

40,000

September

125,000

38,500

October

100,000

 

November

87,000

 
 

The four Lower Snake River dams (Lower Granite, Lower Monumental, Little Goose, and Ice Harbor) along with the John Day Dam are breached.

One MAF of non-treaty water stored in the Mica Reservoir is used along with an additional 900,000 acre-feet of water from the Arrow Reservoir to aid in achieving the flow objectives in Table F-5.

One MAF of water diverted from Banks Lake are used to help achieve the flow objectives in the Columbia River.

An additional 500,000 acre-feet of water from the Brownlee Reservoir is used to aid in flow augmentation from July through September in the Snake River. This is in addition to the volume provided under the 1998 biological opinion.

An additional 1 MAF of water from the Upper Snake River Basin is to be acquired, whenever possible, to aid in achieving the flow objectives. (This water is in addition to the 427,000 acre-feet provided in the 1998 biological opinion).

During winter months, the outflow at federal dams is reduced to minimum levels to fill the reservoirs as much as possible for the upcoming migration season. Flood control elevations are not violated.

Variable-flow flood control limits are implemented at Libby, Hungry Horse, and Grand Coulee dams. This allows more space in the Libby and Hungry Horse reservoirs to store water for flow augmentation. In addition, flood control space is further reduced at Grand Coulee by a maximum of an additional 1.8 MAF and at Dworshak by a maximum of 600,000 acre-feet and at Brownlee by a maximum of 200,000 acre-feet. This reduction in flood control space will increase the risk of flooding downstream. No assessment was made as to the magnitude or cost of the increased risk.

Integrated rule curves are not used in this alternative.

During the migration period between April and June, Dworshak Reservoir is not drafted below 1,495 feet for flow augmentation. In July, August, and September, Dworshak’s minimum draft elevation is 1,520, 1,535, and 1,520 feet, respectively.

Grand Coulee is not drafted below 1,277.6 feet (2150 KSFD) in August for flow augmentation.

End-of-August draft limits at Libby and Hungry Horse dams are the same as under the 1998 biological opinion.

 

Alternative 3: A Strong Snake River Ecologically Connected to the Columbia River To Aid Harvest

An ecosystem that is maintained in a state that facilitates existing salmon harvest patterns and provides increased harvest opportunities. The system would provide increased levels of harvest, ecological services, and intrinsic benefits as well as significant conventional economic services.

Under this alternative, Snake River fall chinook salmon numbers will be built up to eliminate the mixed-harvest conflict with the more robust populations of Hanford Reach fall chinook salmon. Other tributary areas supporting other species are ecologically healthy. Transportation and generation in the Lower Snake are eliminated.

Modeling Assumptions

In this alternative, the water budget flow objectives at McNary Dam established in the 1998 biological opinion are implemented in every year. (In the 1998 biological opinion, the flow objectives in dry years are waived.)

All water budget flow objectives for the Snake River are removed.

The four Lower Snake River dams (Lower Granite, Lower Monumental, Little Goose, and Ice Harbor) along with the John Day Dam are breached.

Integrated rule curve limitations are observed at Libby and Hungry Horse dams.

As in the 1998 biological opinion operation, water from the Libby Reservoir is used to augment flows for sturgeon in May, June, and July. However, in this alternative, priority is given to the integrated rule curve operation in those months. Thus, flows for sturgeon are augmented only if Libby’s elevation does not drop below the integrated rule curve level.

Up to 3 to 5 MAF of non-treaty water from the Mica Reservoir are used, whenever available for flow augmentation in the Columbia River.

Unlike the 1998 biological opinion operation, that attempts to refill federal reservoirs in June to provide more water for August flow augmentation, this alternative gives the June flow objectives a higher priority. The hope was that with the additional non-treaty water from Mica, July and August flows would not be greatly reduced.

Spring and summer flow targets are based on the 1998 biological opinion standard, except at Lower Granite Dam.

Use water from the Grand Coulee reservoir (within limits) and from non-treaty storage to maintain a minimum flow at Bonneville Dam of 125,000 cubic feet per second from November through April for Chum salmon. Drafting limits at Grand Coulee for this operation are set at 1,269.3 feet in November and 1,264.3 feet in December.

The same spill is provided as in the 1998 biological opinion.

The variable-flow flood control elevations at Libby, Hungry Horse, and Grand Coulee reservoirs are used in this alternative.

Dworshak is not used for flow augmentation at McNary Dam.

 

Alternative 5: Rebuild Fish and Wildlife Without Major System Reconfiguration

Build healthy and harvestable salmon and resident fish populations and stabilize weak stocks while preserving current benefits of multipurpose dams. Mitigate for loss of wildlife habitat while respecting private property rights.

Modeling Assumptions

The 1998 biological flow objectives at Lower Granite and McNary dams are implemented in this alternative.

Use up to 3 to 5 MAF of Mica non-treaty storage for flow augmentation in the Columbia River.

No operation for chum salmon is included in this alternative.

The integrated rule curve limitations are not implemented in this alternative.

Unlike the biological opinion operation, that attempts to refill federal reservoirs in June to provide more water for August flow augmentation, this alternative gives the June flow objectives a higher priority. The hope was that with the additional non-treaty water from Mica, July and August flows would not be greatly reduced.

Bypass spill for fish passage is increased to the levels indicated in Table F-6.

Table F-6

Juvenile Bypass Spill Requirements

(cubic feet per second for 24 hours, unless otherwise noted)

Project

 

Spill Level

 

Lower Granite

80,000

Little Goose

70,000

Lower Monumental

70,000

Ice Harbor

100,000

McNary

160,000

John Day

180,000

The Dalles

64 % of flow

Bonneville

175,000

 

No dams are breached in this alternative.

The variable-flow flood control elevation limits at Libby, Hungry Horse, and Grand Coulee reservoirs are used in this alternative.

 

Alternative 6: Rebuild Species By Making Limited Adjustments In Current River Operations

Build healthy, harvestable salmon and resident fish populations and stabilize weak stocks at acceptable cost while maintaining existing types and levels of economic and social benefits. Mitigate for loss of wildlife habitat while respecting private property rights.

This alternative would allow for making limited adjustments in river operations for fish, increasing investment in habitat and other measures, and reducing mixed-stock harvest. Like Alternative 5, this alternative aims to build a healthy, harvestable salmon populations and stabilize weak stocks at an acceptable cost.

Modeling Assumptions

This alternative keeps most of the operations in the 1998 biological opinion.

All spring flow objectives for the Snake and Columbia rivers are removed.

Variable-flow flood control elevation limits are implemented at Libby, Hungry Horse, and Grand Coulee dams.

Integrated rule curve drafting limits are imposed at Libby Dam year round.

Integrated rule curve drafting limits are imposed at Hungry Horse Dam from January through August (no IRC operation is applied from September through December to minimize water forced out in spring due to flood control).

Bypass spill requirements are removed at the collector dams (Lower Granite, Little Goose, Lower Monumental, and McNary).

The Brownlee Reservoir contributes 500,000 acre-feet of water in late summer for flow augmentation.

Dworshak is kept as full as possible through July. In August, 1 MAF of water is used for flow augmentation.

Draft limits at federal reservoirs in spring and summer months for flow augmentation are the same as in the 1998 biological opinion.

The 1998 biological opinion requirement to fill Libby, Hungry Horse, and Grand Coulee reservoirs during the winter months is removed.

 

Alternative 7: Rebuild species while maintaining all current river uses

Develop the Columbia River Basin primarily to maintain and enhance existing types of economic returns and services. Institute fish and wildlife mitigation that provides positive economic return to harvest and other social benefits.

This alternative would make major adjustments in current river operations to finance habitat and other measures, and would eliminate mixed-stock harvest. Like Alternatives 5 and 6, this alternative aims to build a healthy, harvestable salmon populations and stabilize weak stocks at an acceptable cost.

Modeling Assumptions

The modeling assumptions for this alternative are based on a pre-water budget operation (circa 1980). The system is optimized for power production while maintaining flood control and other miscellaneous non-power constraints. All fish and wildlife constraints (as described in Alternative 4 under the 1998 biological opinion) have been removed. This alternative provides no bypass spill at any project.

Besides not imposing any fish and wildlife constraints on the system, the rule curves developed for this alternative were optimized to maximize power production.

Summary of Results

While the amount of data produced by the HYDSIM program can be voluminous, the tables in this section include only the data (with one exception) that were forwarded to the Human Effects and Ecological work groups. Those data summarizes the monthly changes in hydroelectric generation and in river flows. To be a little more complete, a summary of monthly changes to reservoir elevations is also included. Other study results can be summarized fairly easily if the need arises.

Data to the Human Effects Group (Hydroelectric Generation)

These data include the 50-year average monthly hydro generation for each alternative. This generation does not include generation from hydro-independent dams and does not take into account the generation required for pumping at Grand Coulee Dam. Table F-7 provides the average monthly generation for each alternative and Table F-8 provides the differences in monthly generation relative to Alternative 4.

Data to the Ecological Group (River Flows)

These data include the 50-year average monthly river flows at Priest Rapids, McNary, and Lower Granite dams in cubic feet per second. In addition, monthly river flows for a typical wet year (1969) and a typical dry year (1973) are included. Tables F-9 to F-11 summarize the average, wet, and dry year flows at Priest Rapids Dam. Tables F-12 to F-14 summarize the flows at The Dalles Dam. Tables F-15 to F-17 summarize the flows at Lower Granite Dam.

Other Pertinent Results (Reservoir Elevations)

In addition to the data above, the 50-year average monthly elevations at Libby, Hungry Horse, Grand Coulee, Dworshak, and Brownlee dams are included. These monthly average elevations are shown in Tables F-18 to F-22 in units of feet above sea level and are rounded to the nearest foot.

 

Table F-7

 

50-Year Average Hydro System Generation

(average megawatts)

Alternative 

1

September

 

7062

10171

8183

9106

9297

9053

10791

October

 

7905

8475

8405

10268

10372

10244

11468

November

 

7933

9347

11465

10714

10691

10694

13075

December

 

10959

12290

13067

14001

14277

14104

15176

January

 

11691

12799

15921

17514

15693

17544

19073

February

 

11972

12648

15197

15818

14988

15782

16906

March

 

12604

12036

11470

12303

12040

12574

15059

Apr 1-15

 

14256

13129

13091

14062

13474

15010

14265

Apr 16-30

 

11955

14220

14299

15071

14455

15021

15553

May

 

15023

15765

15552

17200

15817

17365

18105

June

 

15725

16694

15395

17564

16514

17926

17945

July

 

13506

13855

12536

14222

14429

14228

13755

Aug 1-15

 

9995

12200

11394

12613

12953

12049

12616

Aug 16-31

 

8196

9847

10514

10940

11974

11536

10305

Average

 

11379

 

12392

 

12636

 

13744

 

13373

 

13851

 

14797

 

 

Table F-8

 

Difference in the 50-Year Average Generation from Alternative 4

(average megawatts)

Alternative 

3

4

September

 

-2043

1065

-923

0

192

-52

1686

October

 

-2363

-1793

-1863

0

104

-24

1200

November

 

-2781

-1367

751

0

-23

-20

2361

December

 

-3042

-1711

-934

0

276

103

1175

January

 

-5822

-4715

-1593

0

-1821

30

1559

February

 

-3847

-3170

-621

0

-830

-36

1088

March

 

301

-267

-833

0

-263

271

2756

Apr 1-15

 

194

-933

-971

0

-588

948

203

Apr 16-30

 

-3116

-851

-772

0

-616

-50

482

May

 

-2177

-1435

-1648

0

-1383

165

905

June

 

-1839

-870

-2169

0

-1050

362

381

July

 

-716

-367

-1686

0

207

6

-467

Aug 1-15

 

-2618

-413

-1219

0

340

-564

3

Aug 16-31

 

-2744

-1093

-426

0

1034

596

-635

Average

 

-2364

 

-1352

 

-1107

 

0

 

-371

 

108

 

1053

 

Table F-9

 

50-Year Average Flows at Priest Rapids Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

63133

84932

61984

71728

71757

71859

80645

October

 

67771

69453

64842

79317

79979

79598

83815

November

 

57068

71160

87218

77075

76653

76583

89001

December

 

91793

102223

103602

107495

110220

105129

109554

January

 

90283

112860

143371

153594

129056

153050

172287

February

 

104735

112911

143008

139802

127177

134211

142527

March

 

129330

101881

90744

87457

83980

89452

117525

Apr 1-15

 

138372

108915

109900

101981

104917

112875

101223

Apr 16-30

 

125964

143429

143193

127091

139546

124971

118771

May

 

192575

185386

177367

171988

175414

169397

160807

June

 

213105

206710

174122

177453

178379

177841

154381

July

 

174708

153777

135016

135133

144988

139030

107909

Aug 1-15

 

119538

130557

124888

119141

130691

115872

109020

Aug 16-31

 

91452

97017

109402

100403

117249

103251

85407

 

Table F-10

 

Wet Year (1969) Flows at Priest Rapids Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

90733

105586

76175

96674

98470

96574

105537

October

 

84820

82966

76873

96191

96178

96941

98101

November

 

75659

88166

77720

87266

86102

84273

101750

December

 

101202

118619

122764

119803

121835

116817

120874

January

 

109491

137861

178424

187158

148799

192416

213809

February

 

156011

155237

195874

179793

144302

169933

161302

March

 

132403

120547

86462

95237

97814

103413

118216

Apr 1-15

 

153630

106930

123123

126066

118408

120449

153653

Apr 16-30

 

193028

174845

156353

158930

153767

151483

197047

May

 

264650

256600

243727

245965

239157

240750

239438

June

 

223560

239125

204019

204241

201441

204438

171441

July

 

166338

142003

135011

116646

147148

129092

83889

Aug 1-15

 

103488

125614

108936

113947

132719

103375

86474

Aug 16-31

 

78842

82444

99535

77267

111699

86402

63518

Table F-11

 

Dry Year (1973) Flows at Priest Rapids Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

62156

100567

69703

83166

80468

82187

78275

October

 

66099

70753

71005

80447

78111

77662

81437

November

 

51367

65665

80599

66613

64190

66177

79283

December

 

87261

106954

106827

105099

110019

102138

110711

January

 

88189

120188

156897

159508

151512

158750

167552

February

 

88892

65369

106165

89815

88341

87082

147662

March

 

63085

80841

69809

63876

64609

63792

75374

Apr 1-15

 

63651

110937

87000

69743

87000

69917

70635

Apr 16-30

 

88064

116129

160988

128767

154453

151854

76440

May

 

128937

116152

149343

109641

141550

105844

82382

June

 

159045

150134

104054

116531

130363

107634

85053

July

 

122545

95886

55633

75207

73072

71329

90695

Aug 1-15

 

99894

113603

91075

89913

97061

86573

87056

Aug 16-31

 

75896

87696

77549

66056

79433

69525

62309

 

Table F-12

50-Year Average Flows at The Dalles Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

95782

127103

95920

99886

100559

97744

115924

October

 

101734

95752

97184

109622

110284

109903

121322

November

 

99269

103180

124770

109304

108882

109227

134559

December

 

141929

149409

155285

155839

158564

154962

165009

January

 

144790

162926

199793

207900

183362

209157

231579

February

 

167862

166863

202094

198279

185654

193261

205257

March

 

196562

168129

157798

154250

150772

156489

189044

Apr 1-15

 

229957

197696

200848

197283

200169

208204

190663

Apr 16-30

 

233277

247610

254678

238358

250528

236455

217588

May

 

306990

310658

292272

287186

290611

283715

269213

June

 

326017

322553

286556

290140

291174

290864

260624

July

 

226777

212786

188879

195951

205706

197443

157813

Aug 1-15

 

159049

183823

166777

172068

183659

165387

142593

Aug 16-31

 

121782

146099

140135

139319

155218

146491

113825

Table F-13

Wet Year (1969) Flows at The Dalles Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

125978

149251

113175

126188

129088

123755

145364

October

 

124778

109185

114876

130375

130362

131125

140943

November

 

130429

129115

126424

128258

127094

128368

155779

December

 

149665

164331

173946

166297

168330

167999

175352

January

 

190327

209728

260964

269698

231338

274955

298319

February

 

229680

220241

265171

249090

213599

239230

228873

March

 

214412

202148

168339

177114

179691

185290

204726

Apr 1-15

 

285437

237128

254157

261520

253862

255903

291165

Apr 16-30

 

343359

324774

311344

313921

308758

306474

346379

May

 

430311

440989

409143

411381

404573

406166

399500

June

 

326425

343496

307427

310298

307498

307846

268811

July

 

213535

195194

183793

176508

207009

184215

129213

Aug 1-15

 

135000

179219

142536

159803

178575

141634

117349

Aug 16-31

 

105000

140000

129868

108295

142728

128766

88588

Table F-14

Dry Year (1973) Flows at The Dalles Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

100257

143822

107448

115365

112667

112053

118632

October

 

101625

99016

104575

112284

109948

109500

123030

November

 

96517

100682

119691

101312

98888

100876

127137

December

 

139779

157757

162056

156482

161402

155231

169181

January

 

149009

175323

219420

222031

214035

221274

232287

February

 

128854

97377

143198

126848

125374

124115

190679

March

 

108588

127689

114024

108092

108824

108007

132317

Apr 1-15

 

104368

156435

126762

113926

131182

114101

114876

Apr 16-30

 

136068

165884

213527

181304

206992

204391

127133

May

 

204049

191334

227807

188105

220013

182521

152476

June

 

217703

210759

161199

173675

187508

166626

134370

July

 

153527

132205

88401

120439

118305

110440

118395

Aug 1-15

 

135000

149493

123477

135015

142163

123948

111434

Aug 16-31

 

104845

126172

105632

95440

108817

109639

89812

Table F-15

50-Year Average Flows at Lower Granite Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

24609

34370

26273

22655

22655

20383

26869

October

 

25306

17889

26091

24054

24054

24054

26261

November

 

30946

20790

26251

20928

20928

21343

33176

December

 

35101

31298

35795

32456

32455

33944

41124

January

 

37893

33519

39875

37760

37760

39561

42849

February

 

44113

35085

40219

39610

39610

40184

42863

March

 

48669

47863

48669

48407

48407

48651

52247

Apr 1-15

 

75290

72452

75290

76361

76559

76638

72411

Apr 16-30

 

93575

90305

93575

93270

93072

93575

84582

May

 

106369

117531

106954

107245

107245

106309

102691

June

 

100399

103585

99795

100156

100156

100399

97210

July

 

42271

49164

44058

50913

50913

48493

40355

Aug 1-15

 

30346

43995

32558

43643

43637

40231

23706

Aug 16-31

 

23199

41104

23362

30599

30598

34923

21182

Table F-16

Wet Year (1969) Flows at Lower Granite Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

30308

39322

32064

27199

27199

24866

34016

October

 

33064

19786

33409

29590

29590

29590

33255

November

 

42806

28985

36739

29027

29028

32130

41989

December

 

37674

33768

39238

34550

34550

39238

43251

January

 

61510

52892

63565

63565

63565

63565

66022

February

 

61165

52865

57158

57158

57158

57158

53539

March

 

64115

63839

64115

64115

64115

64115

68386

Apr 1-15

 

100399

99564

100399

101786

101786

101786

111419

Apr 16-30

 

116559

115650

116559

116559

116559

116559

115142

May

 

136391

155364

136391

136391

136391

136391

130994

June

 

82156

83452

82156

84805

84805

82156

78613

July

 

37296

43493

39083

50163

50163

45425

35465

Aug 1-15

 

30000

52092

32089

44344

44344

36747

28377

Aug 16-31

 

22980

50872

23649

24344

24344

35680

21536

 

 

Table F-17

Dry Year (1973) Flows at Lower Granite Dam

(cubic feet per second)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

30767

35921

30410

26382

26382

24049

32170

October

 

26805

19510

27150

25416

25416

25416

30172

November

 

35818

25675

29751

25357

25357

25357

38441

December

 

39518

36658

41082

37237

37237

38946

45041

January

 

45478

40144

47533

47533

47533

47533

49061

February

 

30672

21640

26665

26665

26665

26665

33492

March

 

32387

35019

32386

32387

32386

32387

40084

Apr 1-15

 

35218

37339

35218

36605

36605

36605

35918

Apr 16-30

 

39871

41992

39871

39871

39871

39871

40573

May

 

70013

69904

71800

71800

71800

70013

66523

June

 

56252

58220

54406

54406

54406

56252

51216

July

 

26667

32004

28454

40917

40917

34796

24691

Aug 1-15

 

30000

30784

27296

39996

39996

32269

18776

Aug 16-31

 

20000

29527

19134

20435

20435

31165

17672

Table F-18

50-Year Average Elevations at Libby Dam

(feet above sea level)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

2453

2443

2445

2432

2436

2441

2449

October

 

2454

2429

2444

2426

2430

2434

2442

November

 

2446

2419

2427

2419

2424

2429

2426

December

 

2412

2411

2411

2411

2411

2411

2403

January

 

2402

2402

2396

2385

2402

2402

2378

February

 

2388

2386

2373

2361

2386

2386

2349

March

 

2380

2378

2359

2347

2378

2378

2335

Apr 1-15

 

2379

2378

2357

2347

2377

2377

2334

Apr 16-30

 

2383

2382

2362

2352

2382

2382

2338

May

 

2407

2406

2397

2380

2417

2406

2388

June

 

2442

2439

2442

2423

2450

2441

2440

July

 

2454

2447

2457

2440

2449

2451

2451

Aug 1-15

 

2453

2445

2455

2439

2446

2451

2452

Aug 16-31

 

2452

2446

2452

2438

2441

2449

2452

Table F-19

50-Year Average Elevations at Hungry Horse Dam

(feet above sea level)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

3556

3538

3545

3537

3537

3544

3526

October

 

3554

3533

3542

3533

3533

3541

3514

November

 

3552

3531

3541

3531

3531

3540

3502

December

 

3546

3522

3532

3522

3522

3531

3490

January

 

3521

3524

3517

3510

3513

3519

3479

February

 

3505

3519

3500

3503

3505

3507

3467

March

 

3497

3507

3481

3499

3501

3500

3455

Apr 1-15

 

3489

3494

3479

3490

3498

3491

3455

Apr 16-30

 

3498

3503

3486

3492

3502

3499

3466

May

 

3529

3532

3520

3525

3529

3530

3508

June

 

3556

3552

3550

3552

3552

3556

3536

July

 

3559

3550

3557

3552

3555

3557

3540

Aug 1-15

 

3559

3547

3555

3548

3550

3555

3537

Aug 16-31

 

3558

3546

3550

3543

3543

3549

3535

Table F-20

50-Year Average Elevations at Grand Coulee Dam

(feet above sea level)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

1290

1280

1283

1287

1287

1288

1288

October

 

1290

1286

1282

1287

1288

1288

1288

November

 

1290

1288

1284

1288

1288

1289

1288

December

 

1290

1278

1275

1278

1278

1285

1285

January

 

1290

1289

1263

1266

1265

1267

1265

February

 

1284

1289

1241

1245

1246

1251

1244

March

 

1255

1278

1242

1246

1243

1249

1218

Apr 1-15

 

1241

1274

1239

1242

1239

1241

1217

Apr 16-30

 

1238

1266

1235

1240

1235

1238

1221

May

 

1257

1269

1252

1257

1252

1257

1245

June

 

1287

1280

1284

1286

1284

1287

1283

July

 

1290

1284

1286

1286

1287

1286

1289

Aug 1-15

 

1290

1280

1281

1281

1283

1282

1289

Aug 16-31

 

1290

1279

1280

1280

1280

1280

1290

 

Table F-21

50-Year Average Elevations at Dworshak Dam

(feet above sea level)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

1583

1520

1586

1531

1531

1554

1572

October

 

1579

1522

1581

1533

1533

1556

1567

November

 

1568

1527

1568

1537

1537

1559

1551

December

 

1557

1534

1557

1541

1541

1556

1531

January

 

1539

1541

1539

1531

1531

1538

1511

February

 

1522

1540

1522

1517

1517

1522

1488

March

 

1514

1539

1514

1511

1511

1514

1474

Apr 1-15

 

1515

1544

1515

1511

1511

1514

1478

Apr 16-30

 

1518

1551

1518

1516

1516

1518

1495

May

 

1571

1571

1571

1567

1567

1571

1558

June

 

1598

1598

1598

1594

1594

1598

1591

July

 

1600

1600

1600

1570

1570

1600

1591

Aug 1-15

 

1591

1579

1600

1549

1549

1581

1589

Aug 16-31

 

1590

1553

1600

1532

1532

1556

1587

Table F-22

50-Year Average Elevations at Brownlee Dam

(feet above sea level)

Alternative

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

September

 

2077

2015

2050

2050

2050

2050

2077

October

 

2077

2048

2048

2048

2048

2048

2077

November

 

2077

2073

2073

2073

2073

2073

2074

December

 

2077

2070

2070

2070

2070

2070

2060

January

 

2077

2060

2060

2060

2060

2060

2035

February

 

2064

2071

2064

2064

2064

2064

2034

March

 

2057

2065

2057

2057

2057

2057

2012

Apr 1-15

 

2049

2061

2049

2050

2049

2049

2012

Apr 16-30

 

2036

2052

2036

2036

2036

2036

2012

May

 

2060

2060

2057

2057

2057

2060

2052

June

 

2077

2077

2077

2077

2077

2077

2076

July

 

2077

2042

2069

2069

2069

2045

2077

Aug 1-15

 

2077

2041

2050

2050

2050

2035

2077

Aug 16-31

 

2077

2044

2048

2048

2048

2035

2077

 

Table F-23

Summary of Alternatives

 

Framework Alternatives

 

 

Hydro Strategies

 

1

 

2

 

3

 

4

 

5

 

6

 

7

 

Configuration

 

Lower Snake Dams

Breach

Breach

Breach

Test

98 Bi-Op

98 Bi-Op

Pre WB

John Day

Breach

Breach

98 Bi-Op

98 Bi-Op

98 Bi-Op

98 Bi-Op

Pre WB

McNary

Breach

98 Bi-Op

98 Bi-Op

98 Bi-Op

98 Bi-Op

98 Bi-Op

Pre WB

Gas abatement

Yes

Yes

Yes

Test

Test

Yes

No

Surface bypass

Yes

Yes

Yes

Test

Test

Test

Test

JBS/screens

Yes

Yes

Yes

Test

Test

Test

Test

 
 

Operational

 

Flood control changes

VAR Q

VAR Q
+

VAR Q

Test

VAR Q

VAR Q

No

Storage rule curves

IRCs

No

IRCs

Test

Test

IRCs
-

No

Flow objectives

Normative hydrograph+

Normative hydrograph

98 Bi-Op Columbia only

Test

98 Bi-Op

Summer only
-

No

Additional Upper Snake water

No

Yes

No

Test

No

No

No

Additional Canadian water

Yes

Yes

Yes

No

Yes

No

No

Minimize flow fluctuations

Yes

Yes

Yes

Test

Yes

Hanford only

No

Temperature control

Yes

Yes

Yes

Test

Yes

Yes

No

 
 

Passage

 

Smolt transport

No

No

No

Spread Risk

Spread Risk

Yes
Spring and Summer

Max

Fish spill

Yes

Yes

Yes

Test
+ and -

Yes
+

Yes
-

No

Turbine improvements

Yes

Yes

Yes

Yes

Yes

Yes
+

Yes

JBS = Juvenile Bypass System IRCs = Integrated Rule Curves
98 Bi-Op = At 1998 Biological Opinion levels Col = Columbia River
Pre WB = At pre-Water Budget levels SN = Snake River
Test = Develop and Test or Experiment + = More than the specified level
VAR Q = Variable Flow Flood Control - = Less than the specified level